Hillsdale Boulevard & Alameda de las Pulgas Traffic Signal Project
Ways to Get Involved
- Watch a virtual recording of the community meeting held online on Thursday, October 16, 2025 - Watch or Listen to the October 16, 2025 Community Meeting
- View the Final Hillsdale Boulevard and Alameda De Las Pulgas Traffic Signal Design Concepts that was developed after the January ’24 community meeting.
- Refer to the project timeline at the bottom of this project website for current project status. Staff will keep this timeline updated as we get closer to project implementation (project council award to construction).
About the Project
The City of San Mateo will install a new traffic signal at the intersection of Alameda de las Pulgas and Hillsdale Boulevard (see project area map below). The project will improve how people travel through the intersection by way of walking, biking, rolling, driving, and taking transit. In 2017, a traffic signal was requested at the intersection through the Hillsdale/Beresford Traffic Action Plan. Staff conducted a signal warrant analysis to determine if the intersection would qualify for a signal based on engineering metrics and requirements and found that the intersection met the conditions to justify a traffic signal installation.
The project will include:
- Slurry seal work at the intersection.
- Partially protected intersection to facilitate bike movements, shorten crossing distances for pedestrians, and force more right-angle turns for drivers.
- Installation of traffic signal equipment:
- Accessible pedestrian signals
- Improved safety lighting
- Vehicle signals
- Protected left turns on Alameda de las Pulgas:
- New lane striping at the intersection.
- New crosswalk striping at the intersection.
We would like feedback from the community on the final design for the intersection which seeks to ensure safety for all users and reduce congestion at Alameda de las Pulgas & Hillsdale Boulevard.
View the final project design at this link: Final Signal Project Design Concept. Please refer to the virtual meeting recording within the “Ways to Get Involved” section. Staff will be incorporating additional feedback received from the public in the follow-up October 2025 meetings within the final designs and hold to the project timeline as below to implement both the signal and intersection improvements necessary for this project.
Project Materials
- Project Design Concepts 2024
- Preferred/Revised Design Concepts 2025
- Final Design Concept: Addressing Public Feedback
- Jan. 29, 2024: Hillsdale Branch Library Community Workshop Presentation
- Community Workshop & Email Feedback
Contact
Sang Hee Cho
Project Manager
scho@cityofsanmateo.org
Related Documents
Project Updates
November 2026
The Project was advertised for construction bids in October 2026, and the apparent low bidder has been identified. Staff anticipates bringing the construction contract for this project to City Council for award by the end of 2026. The Project remains on track with the schedule shown in the project timeline below.
Project Location
Map description: The map shows the proposed project location at the intersection of Alameda de las Pulgas and Hillsdale Boulevard in San Mateo. The project is located near Abbott Middle School and Hillsdale High School to the west and Hillsdale Branch San Mateo Public Library and Laurel Elementary School to the east. West Hillsdale Park and East Hillsdale Park are located north of Hillsdale Boulevard. The map includes a north arrow and a scale indicating 0 to 500 feet.
Project Timeline
The project timeline includes the following activities and anticipated schedule:
Fall 2023 – Spring 2024
Traffic Analysis
Stakeholder and Community Engagement
Fall 2023 – Winter 2024
Preliminary Design
Spring 2024 – Fall 2025
Project Design
Summer – Fall 2025
Follow-Up Community Engagement
2024 – 2026
S&I Bike & Ped Updates
Winter 2026
Project Bid and Award
Summer 2027
Construction Project